ROADS SECTOR
PR
engineering circle, Khammam has a total rural road length of
5995.52 Kms., out of which CC roads are 58.07 Kms., BT roads
620.48 Kms., WBM roads are 1782.60 Kms., Gravel roads are 2325.22
Kms., and formation of roads 1209.15 Kms., including 3708 pipes
culverts, 639 slab culverts, 341 road dams and 122 Major &
Minor Bridges.
1 NABARD PROGRAMME:
Under this programme 5 works (4 roads & 1 bridge)
were sanctioned with an estimated cost of Rs.624.50 lakhs in
which one work is completed, two works are nearing completion
stage and the balance two works are in progress.
a) Length taken up : 40.80 KMs
b) No.of villages benefitted : 35
2 PMGSY (Phase-II)
Under this programme 39 roads are taken up with
at estimated cost of Rs. 1673.33 lakhs in which 34 roads are
completed with a financial value of Rs.1315.96 lakhs. Balance
five works are in progress and will be completed by end of September,
2004.
a) Length taken up : 147.55 KMs
b) No.of villages benefitted : 45
c) Population Served : 53425
3 PMGSY (Phase-III)
Sanction is accorded for an amount of Rs. 1497.97
lakhs for providing connectivity to the unconnected habitations
of 28 villages i.e. in Tribal mandals such as Tekulapalli, Singareni,
Mulkalapalli, Chintoor, Pinapaka, Kukunoor and V.R.Puram. Some
of the works are in progress.
a) Length taken up : 106.90 KMs
b) No.of villages benefitted : 28
c) Population Served : 12438
4 R.R.M.
Under this programme, 111 balance works are taken
up with an estimated cost of Rs. 282.51 lakhs and will be completed
during the year 2004-2005.
5 MNP
Under this programme, 34 works are taken up at
estimate cost of Rs.242.00 lakhs and value of work done Rs.195.00
lakhs. Out of which 10 works are completed and government have
asked to close the works at safer stage due to paucity of funds.
6 Agricultural Market Committee (AMC)
Under this programme, 163 works are taken which
are tied up with food component at an estimated cost of Rs.424.00
lakhs. Out of which 141 works are completed and expenditure
incurred Rs. 377.00 lakhs. The balance works are nearing completion.
7 D.C.P.
Under this programme, 36 works are taken up at
an estimated cost of Rs.101.60 lakhs. Out of which 11 works
are completed duly incurring expenditure of Rs.24.92 lakhs.
Balance works are in progress.
BUILDINGS SECTOR
8 STATE PLAN
Under this programme, Construction of one M.P.P.
Building is taken up at an estimated cost of Rs. 25.00 lakhs
and it is under progress.
9 D.P.E.P.
Under this programme, 390 works (Construction of
Addl. Class rooms, compound walls and teacher training centers)
are sanctioned at estimated cost of Rs.354.45 lakhs. 97 works
are completed and the balance works are at different stage.
Release of grant is delayed. Slow progress is attributed to
steep rise in cost of steel and cement.
IRRIGATION SECTOR
10 MINOR IRRIGATION
There Are 2097 MI tanks with an ayacut of 21931.50
Hectares under the control of P.R.Circle, Khammam. In the last
3 years, restoration of 512 MI tanks was taken up by P.R.Department
in Neeru-meeru programme under different grants such as NABARD-MI,
XI Finance, SGRY, Drought etc. Now an amount of Rs. 29.65 lakhs
is released in 1 st quarter of MI (Normal) grant. With this
amount is proposed to take up permanent restoration of 28 MI
tanks, which were damaged due to heavy rains and floods during
August 2003. Temporary restoration was already done with an
amount of Rs. 4.01 lakhs under MI (Normal) grant in the year
2003-04. To the extent of maximum possible, the proposals for
repairs to MI tanks being sanctioned at Mandal level. Remaining
proposals are being sent to Zilla Parishad for approval. The
District Z.P. body also willing to clear the MI proposals on
top priority.